• ০০। A company spends considerable amount on publicity to promote sales. This expenditure in break even chart is shown below the
    • ক) fixed cost line
    • খ) variable cost line
    • গ) total cost line
    • ঘ) sales revenue line
  • ০১। A critical activity has
    • ক) maximum slack
    • খ) minimum slack
    • গ) zero slack
    • ঘ) average slack
  • ০২। A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called
    • ক) hoist
    • খ) jib crane
    • গ) portable elevator
    • ঘ) chain conveyor
  • ০৩। A diagram showing the path followed by men and materials while performing a task is known as
    • ক) string diagram
    • খ) flow process chart
    • গ) travel chart
    • ঘ) flow diagram
  • ০৪। A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).
    • ক) Correct
    • খ) Incorrect
  • ০৫। A dummy activity in a net work diagram
    • ক) is represented by a dotted line
    • খ) is an artificial activity
    • গ) does not consume time or resources
    • ঘ) all of these
  • ০৬। A feasible solution to the linear programming problem should
    • ক) satisfy the problem constraints
    • খ) optimise the objective function
    • গ) satisfy the problem constraints and non-negativity restrictions
    • ঘ) satisfy the non-negativity restrictions
  • ০৭। A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
    • ক) 0.50
    • খ) 0.66
    • গ) 0.84
    • ঘ) 0.95
  • ০৮। A systematic job improvement sequence will consist of
    • ক) motion study
    • খ) time study
    • গ) job enrichment
    • ঘ) all of these
  • ০৯। A-B-C analysis
    • ক) is a basic technique of materials management
    • খ) is meant for relative inventory control
    • গ) does not depend upon the unit cost of the item but on its annual consumption
    • ঘ) all of the above
  • ১০। A-B-C analysis is used in
    • ক) CPM
    • খ) PERT
    • গ) inventory control
    • ঘ) all of these
  • ১১। Abbreviated work factor data is applied for
    • ক) material handling operation
    • খ) maintenance operation
    • গ) packing and shipping operation
    • ঘ) all of these
  • ১২। Acceptance sampling is used in
    • ক) job production
    • খ) batch production
    • গ) mass production
    • ঘ) all of these
  • ১৩। According to Muther, the basic principle of best layout is
    • ক) principle of over-all integration
    • খ) principle of flow
    • গ) principle of flexibility
    • ঘ) all of these
  • ১৪। According to Rowan plan of wage incentive system, bonus is paid to a worker
    • ক) whose output exceeds 67% efficiency
    • খ) on the percentage of time saved
    • গ) on the percentage of time worked
    • ঘ) on the percentage of standard time
  • ১৫। Actual performance of a task is called
    • ক) an event
    • খ) an activity
    • গ) a duration
    • ঘ) none of these
  • ১৬। An activity of the project is graphically represented by __________ on the network diagram.
    • ক) a circle
    • খ) a straight line
    • গ) an arrow
  • ১৭। An event is a function of two or more activities.
    • ক) Correct
    • খ) Incorrect
  • ১৮। At the break even point,
    • ক) total cost is more than the sales revenue
    • খ) total cost is less than the sales revenue
    • গ) total cost is equal to sales revenue
    • ঘ) fixed cost is equal to variable cost
  • ১৯। Bar chart is suitable for
    • ক) large project
    • খ) major work
    • গ) minor work
    • ঘ) all of these