০০। A construction schedule is prepared after collecting
ক) number of operations
খ) output of labour
গ) output of machinery
ঘ) quantity of various items
ঙ) all the above.
০১। A CPM family includes
ক) CPA (Critical Path Analysis)
খ) CPP (Critical Path Plotted)
গ) MCE (Minimum Cost Expenditure)
ঘ) CPS (Critical Path Scheduling)
ঙ) All the above.
০২। A critical ratio scheduling
ক) establishes the relative priorities among various activities on a common basis
খ) determines the status of each activity
গ) adjusts automatically changes in activity progress
ঘ) is a dynamic system
ঙ) none of these.
০৩। A dummy activity
ক) is artificially introduced
খ) is represented by a dotted line
গ) does not consume time
ঘ) all the above.
০৪। A goiden rule for the procurement of construction stones, suggests
ক) 100% at the site
খ) 67% at the site and 33% under procurement
গ) 50% at the site and 50% under procurement
ঘ) 33% at the site and 67% under procurement
ঙ) none of these.
০৫। A Milestone chart
ক) shows the interdependencies of various jobs
খ) depicts the delay of jobs, if any
গ) points outgoing ahead of schedule of jobs, if any
ঘ) none of these.
০৬। An event is indicated on the network by a number enclosed in
ক) a circle
খ) a square
গ) a triangle
ঘ) an ellipse
ঙ) all the above.
০৭। An Executive Engineer may have powers upto
ক) ৳ 25,000
খ) ৳ 50,000
গ) ৳ 100,000
ঘ) ৳ 200,000
ঙ) ৳ 500,000
০৮। Bar charts are suitable for
ক) minor works
খ) major works
গ) large projects
ঘ) all the Above.
০৯। Completion of an activity on CPM network diagram, is generally known
ক) Event
খ) Node
গ) Connector
ঘ) All the above.
১০। Construction team means
ক) an engineer
খ) an architect
গ) an owner
ঘ) a contractor
ঙ) all the above.
১১। CPM is
ক) synthesising in concepts
খ) is built of activities oriented programme
গ) is based on time estimate
ঘ) is used for repetitive works
ঙ) all the above.
১২। Critical path lies along the activities having total float
ক) positive
খ) negative
গ) zero
ঘ) same.
১৩। Critical path method
ক) is an improvement upon bar chart method
খ) provides a realistic approach to daily problems
গ) avoids delays which are very common in bar charts
ঘ) was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957
ঙ) All the above.
১৪। Critical Path Net Work helps an engineer
ক) to concentrate his attention on critical activities
খ) to divert the resources from non-critical advanced activities to critical activities
গ) to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
ঘ) all the above.
১৫। Final technical authority of a project lies with
ক) Assistant Engineer
খ) Executive Engineer
গ) Superintending Engineer
ঘ) Chief Engineer.
১৬। For completion of a project, the critical path of the network represents
ক) minimum time
খ) maximum time
গ) maximum cost
ঘ) minimum cost.
১৭। For the execution of a project, a contractor is
ক) a person
খ) a firm
গ) an agency
ঘ) all the above.
১৮। For the network shown in the given figure, the expected time for the activity
ক) 1-2 is 4
খ) 2-3 is 7
গ) 3-4 is 8
ঘ) all the above.
১৯। For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is