• ০০। A construction schedule is prepared after collecting
    • ক) number of operations
    • খ) output of labour
    • গ) output of machinery
    • ঘ) quantity of various items
    • ঙ) all the above.
  • ০১। A CPM family includes
    • ক) CPA (Critical Path Analysis)
    • খ) CPP (Critical Path Plotted)
    • গ) MCE (Minimum Cost Expenditure)
    • ঘ) CPS (Critical Path Scheduling)
    • ঙ) All the above.
  • ০২। A critical ratio scheduling
    • ক) establishes the relative priorities among various activities on a common basis
    • খ) determines the status of each activity
    • গ) adjusts automatically changes in activity progress
    • ঘ) is a dynamic system
    • ঙ) none of these.
  • ০৩। A dummy activity
    • ক) is artificially introduced
    • খ) is represented by a dotted line
    • গ) does not consume time
    • ঘ) all the above.
  • ০৪। A goiden rule for the procurement of construction stones, suggests
    • ক) 100% at the site
    • খ) 67% at the site and 33% under procurement
    • গ) 50% at the site and 50% under procurement
    • ঘ) 33% at the site and 67% under procurement
    • ঙ) none of these.
  • ০৫। A Milestone chart
    • ক) shows the interdependencies of various jobs
    • খ) depicts the delay of jobs, if any
    • গ) points outgoing ahead of schedule of jobs, if any
    • ঘ) none of these.
  • ০৬। An event is indicated on the network by a number enclosed in
    • ক) a circle
    • খ) a square
    • গ) a triangle
    • ঘ) an ellipse
    • ঙ) all the above.
  • ০৭। An Executive Engineer may have powers upto
    • ক) ৳ 25,000
    • খ) ৳ 50,000
    • গ) ৳ 100,000
    • ঘ) ৳ 200,000
    • ঙ) ৳ 500,000
  • ০৮। Bar charts are suitable for
    • ক) minor works
    • খ) major works
    • গ) large projects
    • ঘ) all the Above.
  • ০৯। Completion of an activity on CPM network diagram, is generally known
    • ক) Event
    • খ) Node
    • গ) Connector
    • ঘ) All the above.
  • ১০। Construction team means
    • ক) an engineer
    • খ) an architect
    • গ) an owner
    • ঘ) a contractor
    • ঙ) all the above.
  • ১১। CPM is
    • ক) synthesising in concepts
    • খ) is built of activities oriented programme
    • গ) is based on time estimate
    • ঘ) is used for repetitive works
    • ঙ) all the above.
  • ১২। Critical path lies along the activities having total float
    • ক) positive
    • খ) negative
    • গ) zero
    • ঘ) same.
  • ১৩। Critical path method
    • ক) is an improvement upon bar chart method
    • খ) provides a realistic approach to daily problems
    • গ) avoids delays which are very common in bar charts
    • ঘ) was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957
    • ঙ) All the above.
  • ১৪। Critical Path Net Work helps an engineer
    • ক) to concentrate his attention on critical activities
    • খ) to divert the resources from non-critical advanced activities to critical activities
    • গ) to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
    • ঘ) all the above.
  • ১৫। Final technical authority of a project lies with
    • ক) Assistant Engineer
    • খ) Executive Engineer
    • গ) Superintending Engineer
    • ঘ) Chief Engineer.
  • ১৬। For completion of a project, the critical path of the network represents
    • ক) minimum time
    • খ) maximum time
    • গ) maximum cost
    • ঘ) minimum cost.
  • ১৭। For the execution of a project, a contractor is
    • ক) a person
    • খ) a firm
    • গ) an agency
    • ঘ) all the above.
  • ১৮। For the network shown in the given figure, the expected time for the activity
    • ক) 1-2 is 4
    • খ) 2-3 is 7
    • গ) 3-4 is 8
    • ঘ) all the above.
  • ১৯। For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
    • ক) 1
    • খ) 2
    • গ) 3
    • ঘ) 4